Calculate Progress Percent Without Resource Cost

How to calculate the progress percentage of Project and of each WBS in Primavera without assigning cost/resources, activity duration being the only input?

Use Expenses since making use of the Resources and Costs is not intended. In other words, at least some cost has to be incorporated, either as resource cost or as an expense. There doesn’t seem to be another way to generate the progress percent directly from Primavera.