Can you insert a fragnet (separate project schedule) into another project schedule in Primavera P6?

Answer by Fareed A.S.:

The concept of Fragnets doesn’t exist anymore in P6. It is a feature in P3. In a P3 fragnet, a user can store a set of activities along with their full details such as relationships, codes, costs, resources, etc. and use this stored set to be pasted as an entire group in any number of places with a single click, without having to create the same set again and again. This saved immense time and efforts. One way to do this in P6 is to replicate an entire WBS (or more) and the constituent activities will also be replicated with all the details. If this is supposed to be done across projects, you have to open multiple projects at the same time.

Can you insert a fragnet (separate project schedule) into another project schedule in Primavera P6?

Advertisements

Comments

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s