Duration change does not change start/finish date

Sometimes if a schedule is imported from another application, it may happen that an attempt at adding or modifying activities duration will not produce a corresponding change in the dates. The reason this happens is because Remaining Duration does not automatically change to the same value as Original Duration (when adjusting not yet started activities).

This issue can be solved by either maujal adjustments to Remaining Duration, or by global change or in the Project view > Calculations Tab > Check the option of “Link Budget and at completion for not started activities”.

Once this is done, any change to duration will reflect in the dates as well.

Advertisements

Comments

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s